Illustrative · syntheticNot a client result · format sample only
Sample deliverable
Decision memo: concept selection under three risk profiles.
A one-page mock-up of the memo an engagement hands back. The hall, the numbers and the dates are synthetic, so the format can be shown without inventing a client.
Under the Balanced profile, the recommended point is direct-to-chip, W40, with shared reserve and a capping policy.
It is the lowest expected cost whose tail stays inside the stated risk budget. Conservative buys a tighter tail at higher expected cost; Aggressive cuts expected cost by accepting a heavier tail and a later P90 energisation date. None of these figures is a measurement or a client result.
Design points
The same design space, one point for each risk profile.
Conservative
Tighter tail.
Higher expected cost, early gear, reserve left idle.
E[TCO] index
108
CVaR0.95 index
107
P(energised by target)
0.88
Direct-to-chip, W32 facility water, AC, 2N.
Oversubscription held low, so critical jobs are rarely capped.
Cooling sized close to the coincident peak.
Early transformer release, to lift P(energised by the target).
Balanced · recommended
Inside ε, at lower cost.
Lowest expected cost whose tail stays inside the budget.
E[TCO] index
100
CVaR0.95 index
115
P(energised by target)
0.78
Direct-to-chip, W40, shared reserve with a capping policy.
Moderate oversubscription, subject to P[cap on critical] ≤ ε.
Cooling provisioned to a high percentile of the joint load–weather distribution.
Early release only for items on the critical path.
Aggressive
Lower cost, heavier tail.
More capping hours and a later P90 date are accepted.
E[TCO] index
94
CVaR0.95 index
128
P(energised by target)
0.62
Higher oversubscription, with more hours of capping accepted.
Deploy onto reserve power, with fast shedding of non-critical load.
Cooling under-provisioned to a stated percentile, with a defined throttle policy.
Accept a later P90 energisation date, rather than paying for earlier gear.
Schedule
Energisation date, P10 to P90, in weeks from equipment order.
The target is week 150. Each range is the distribution of max(last long-lead delivery + install, interconnection), drawn from triangular lead-time laws. A real memo would fit those laws to quoted lead times and recorded history.
IllustrativeFigureP10–P50–P90 bands by risk profile. The dashed line is the target date. Synthetic data; not a client result.
Balanced P10
138weeks
Balanced P50
156weeks
Balanced P90
182weeks
P(by week 150)
0.78
Uncertainty
Top five drivers of the tail, for the recommended point.
Each bar is the change in CVaR0.95 when that input is moved from a low to a high setting, with the others held at their base values. The register would name the fitted law behind every bar.
IllustrativeFigureTornado on CVaR0.95 (Balanced design = 115). Left: lower tail if the driver eases. Right: higher tail if it tightens. Synthetic data.
Next decisions
What this memo would ask the sponsor to decide.
Adopt the Balanced point as the concept basis, or name a different ε and re-run the frontier.
Release the transformer early, the item that most often sets the energisation date in this sample.
Freeze the W-class and the capping policy before detailed design, so the plant and the software are sized to the same risk budget.
Re-quote long-lead switchgear and interconnection and update the assumption register; the tornado is most sensitive to those two dates.
Decide whether a later scenario simulation (T3) is wanted when quotes or hardware generations change. T3 is a re-run of this model on the documents you send; it does not connect to your systems.
Every number in a real memo traces to the assumption register and the documented simulation model, which are handed over with the report. This page is a format sample only. No client, price or measured result is shown.