Technical notes

Technical notes.

The four practice areas, each as what we model, the key uncertainties, and what the optimiser returns. Then condensed notes. Published figures are cited; illustrative marks worked examples.

The stack

Where uncertainty in AI systems resides.

A qualitative map of the sources we put into the model. Tag shading is a judgement of influence, not a measurement.

IllustrativeFigureWhere uncertainty sits in an AI system stack, and how it couples into cost, schedule and goodput. Tag shading is a qualitative judgement of influence, not a measurement. Click a layer to open the practice area that models it.

Practice areas

What we model, where the uncertainty sits, and what the optimiser returns.

Four blocks, one for each practice area. Layers on the map above jump here.

Illustrative · qualitative

Bar length is a judgement of influence on the objective, not a measurement. The same sources appear in the map above and in the blocks below.

01

Joint software-hardware optimization

Uncertain
GPU failures, job interruptions, training power swings.
We quantify
Goodput per MW, checkpoint interval, spares per pod.

What we model

Scheduler, accelerators and plant as one system: placement, caps, clocks and checkpoints, simulated against UPS headroom, CDU and facility-water capacity, and thermal ride-through.

Key uncertainty sources

Demand mix, model-size growth and job failures; utilisation, checkpoint overhead and goodput; GPU failure rates, thermal throttling and power-draw variance.

What the optimiser outputs

  • Co-design specification: signals and levers, sized by simulation
  • Oversubscription and capping policy, per failure domain
  • Training power-shaping: floors, staggered checkpoints, storage
  • Thermal-headroom envelope for sustained boost

02

Stochastic modeling & optimization

Uncertain
Load, weather, failures and lead times, all at once.
We quantify
Expected cost, its tail (CVaR) and P[miss] against your risk budget.

What we model

Growth, accelerator power, climate, failures, prices and delivery dates as distributions. Monte Carlo and reliability models, then chance-constrained, two-stage programs over them.

Key uncertainty sources

The coupled sources across every layer of the stack — the map above. Uncertainty is not isolated: it propagates into cost, schedule and goodput.

What the optimiser outputs

  • P50 / P90 / P99 envelopes for power, cooling and water
  • Availability, MTTR, spares and SLA exposure
  • min E[TCO] + λ·CVaRα subject to P[excursion] ≤ ε
  • The auditable simulation model, documented and handed over

03

Software/server/electrical/mechanical concept design

Uncertain
Cooling margin at 100 kW+ racks; reserve power left idle.
We quantify
P[thermal excursion] per year; usable reserve capacity.

What we model

Concepts for 100 to ~600 kW racks — cold plate or two-phase immersion (2PIC), AC or 800 VDC, W-class — parameterised and scored together on expected cost and tail risk.

Key uncertainty sources

Rack density; fabric congestion and optics failures; heat rejection, ambient conditions and liquid or immersion capacity; grid-connection timing as a design constraint.

What the optimiser outputs

  • Concept basis across all four disciplines
  • Single-line and heat-rejection concepts for rack, row and hall
  • Technology selection with quantified trade-offs
  • Acceptance criteria and test plans for detailed design

04

Supply chain risk integration

Uncertain
Transformer and switchgear lead times; the grid energisation date.
We quantify
P[energised by target date]; the critical-path items.

What we model

Lead times, sourcing concentration and regulatory exposure (for example PFAS fluids) as distributions, so every design choice carries its delivery risk.

Key uncertainty sources

Transformer and switchgear lead times; vendor concentration; the grid energisation date.

What the optimiser outputs

  • Supply-risk register per BOM line
  • Schedule-risk simulation: P(energisation by date)
  • Design for substitution and second source
  • Procurement inputs: early release, buffers, spec flexibility

Risk profiles

The same design space, three points on the frontier.

Choose a profile to see how the optimiser’s recommended point moves, and which example design choices sit there. Numbers are synthetic.

Illustrative · synthetic

Synthetic numbers for a generic hall, not from any client or project. A real frontier is built from the documents and risk budget you set.

Method

A two-stage, chance-constrained programme over the stack.

Every engagement solves a programme of this form. The depth changes with the tier; the structure does not. The symbols are standard and no site data is shown.

Decision stages

Let x be the here-and-now design (cooling technology, W-class, redundancy, oversubscription, procurement releases, checkpoint and cap policy). Uncertainty is a random vector ξ of IT load and training swings, device failures and MTTR, ambient conditions, prices, and lead times. After ξ is realised, a recourse action y(ξ) is chosen (capping, shedding, chiller trim, flow, restarts).

Objective

minx   Eξ[ TCO(x, y(ξ), ξ) ]  +  λ · CVaRα[ TCO(x, y(ξ), ξ) ]

λ ≥ 0 is the risk appetite agreed at scoping. CVaRα is the expected tail of TCO beyond the α-quantile; it has a standard linear programming representation (Rockafellar–Uryasev) and does not require a non-linear tail oracle.

Chance constraints

Pξ[ Psite(x, y(ξ), ξ) > Pgrid ] ≤ εP
Pξ[ thermal excursion ] ≤ εT
Pξ[ goodput < gmin ] ≤ εG
Pξ[ energise after t* ] ≤ εS

The risk budget (εP, εT, εG, εS) is part of the brief. Constraints may be imposed as empirical frequencies on the sample or as CVaR surrogates when a tail formulation is tighter to enforce.

Scenario generation

Scenarios ξ1 … ξN are drawn by Monte Carlo from distributions fitted to the documents you send, published field data, and quoted lead times. An assumption register records every fitted or assumed law. Optional scenario reduction keeps the tail events that drive CVaR and the chance constraints. The programme is a sample-average approximation (SAA); we report the in-sample objective and, where useful, an out-of-sample check on a held-out draw.

Solver and decomposition

The extensive form (SAA with explicit second-stage copies) is used when N and the design dimension allow. Larger instances are decomposed with an L-shaped / Benders scheme: a master problem on x and CVaR auxiliaries, and subproblems on y(ξn) per scenario or per bundle. Integer first-stage decisions (technology, topology) are handled in the master. We do not require a connection to your systems; the programme is solved on the model built from the design documents and inputs you provide.

TWO-STAGE STOCHASTIC PROGRAMME · ILLUSTRATIVE SCHEMATICSTAGE 1 · HERE AND NOWDesign vector x· cooling technology, W-class· redundancy, oversubscription· procurement releases, buffers· checkpoint / cap / shed policyUNCERTAINTY · SCENARIOS ξSampled ξ₁ … ξ_N· IT load and training swings· failures, MTTR, ambient· lead times, prices, grid dateMonte Carlo / SAA · optional reductionSTAGE 2 · WAIT AND SEERecourse y(ξ)· capping and workload shedding· chiller trim, flow, setpoints· spares, restarts, re-routingOBJECTIVE AND CHANCE CONSTRAINTSmin_x E_ξ [ TCO(x, y(ξ), ξ) ] + λ · CVaR_α [ TCO(x, y(ξ), ξ) ]s.t. P[P_site > P_grid] ≤ ε_P · P[thermal excursion] ≤ ε_T P[goodput < g_min] ≤ ε_G · P[energise after t*] ≤ ε_SCVaR as an LP tail auxiliary. Chance constraints: empirical frequency or CVaR surrogates. Decomposition: SAA, L-shaped / Benders.
IllustrativeFigureSchematic of the programme. The first-stage design x is chosen before uncertainty is realised; second-stage recourse y(ξ) is chosen in each scenario. Not a client result.
NOTE 01

Heat flux, not TDP, sets the cooling regime

DecisionWhich cooling regime a part needs, and how warm the coolant can run.

TDP sets the watts. Peak die heat flux and Tj,max set the technology.

T_j = T_fluid + P · (R_jc + R_TIM + R_cs + R_conv) R_conv = 1 / (h · A_eff) h_air ≪ h_1φ-liquid < h_boiling
Illustrative: 1,000 W at 40 °C coolant and Rj-fluid = 0.045 °C/W gives Tj ≈ 85 °C. Each 0.01 °C/W saved is 10 K of margin: warmer water, higher clocks or lower leakage.
0100200300400500600Rack power (kW)air-cooling limitEnterprise rack (typical)< 10 kW4 × HGX H100, air-cooled≈ 41 kW (4 × 10.2 kW)GB200 NVL72120–132 kWGB300 NVL72135–142 kWVera Rubin NVL72187–227 kW · Max-Q to Max-PKyber-class rack (roadmap)≈ 600 kW · roadmap, GTC 2025
Figure 1Rack power by AI platform, approximate public figures (DCD, Tom's Hardware, Mar 2025). Kyber-class is a roadmap figure.

See UC 02 · Ramakrishnan et al., IEEE TCPMT 2021, doi

NOTE 02

Two-phase immersion: the thermodynamics that matter

DecisionWhether tank and condenser are sized for the vapour load, and the facility-water temperature that allows.

Latent heat sets the vapour flow; the condensate film sets the condenser.

ṁ_vapour = Q / h_fg Q_cond = U · A · ΔT_lm (condensate-film limited) T_sat − T_FWS,in = ΔT_approach → caps facility-water temperature
  • Near-isothermal surfaces at Tsat + ΔTsuperheat; boiling-enhancement coatings raise CHF.
  • Film resistance: a 10 kW rig condensed well below ε-NTU sizing; measured film thickness explained the gap.
  • Production reference: 38U tank, 17.4 kW, 1+1 condensers (OCP 2021).

See UC 01 · Peterson et al., InterPACK 2021, doi · OCP 2021 slides

NOTE 03

Vapour, air and contamination

DecisionWhich containment and filtration to specify before a two-phase rollout.

2PIC programmes slip on containment, not heat transfer.

MechanismEffectControl
Vapour loss (lid-open, extraction, transients)Fluid cost, emissionsSupplemental condensers, air curtains, bellows, high-mounted PRV
Non-condensables in vapour spaceCondenser deratingSpecies separation, purge
Leachates (plasticisers, flux)Boiling-surface residue, hotter partsMaterial elimination, carbon + alumina filtration

Peterson et al., InterPACK 2021, doi · OCP 2021 slides

NOTE 04

Dielectric fluids and PFAS exposure

DecisionWhich dielectric fluid, and the fallback if regulation changes.

Fluid choice fixes Tsat, and with it facility-water temperature and regulatory risk.

  • Fluorinated two-phase fluids sit in the PFAS debate: 3M announced its exit from PFAS manufacturing by end-2025; an EU-wide restriction has been proposed under REACH.
  • We score Tsat, dielectric and material compatibility, GWP, second source and a mid-life fallback design.
Note: regulation moves. We re-check fluid status at the start of each engagement.
NOTE 05

Designing to ASHRAE TC 9.9 envelopes

DecisionWhich supply-temperature class for the facility-water system.

Air: recommended 18–27 °C inlet. Liquid: W-classes W17 to W+, named for maximum facility-water supply.

Warmer W-class: more economiser hours, less ΔT left for the cold-plate stack.

AI rackcold plates, 130 kWCDUliquid-to-liquid HXDry cooler+ trim / adiabaticsupply 37 °Creturn 47 °CTECHNOLOGY COOLING SYSTEM (TCS)supply 32 °C · W32return 42 °CFACILITY WATER SYSTEM (FWS)to ambientdesign Tdb 35 °Capproach ΔT ≈ 5 Kfree cooling while Tdb ≲ 27 °CΔTrack 10 K → ṁ ≈ 3.1 kg/s at 130 kWIllustrative design point, ASHRAE W32 class. Values are worked examples.
Figure 2Heat-rejection path for a direct-to-chip rack at a W32 design point. Illustrative values.

ASHRAE TC 9.9 thermal and liquid-cooling guidelines; confirm against the current edition.

NOTE 06

Power: stranded watts and training swings

DecisionHow far to oversubscribe, and how much storage to buy for training swings.

Reserved power is idle capacity. Synchronous training makes the swing itself a design load.

Oversubscription = Σ P_alloc / P_provisioned − 1 Constraint: P[ P_draw(t) > P_cap ] · cost_cap ≤ budget_SLO ΔP_cluster ≈ N_GPU · (P_compute − P_comm) · α_sync dP/dt ≤ ramp limit
Illustrative: a 20 MW provisioned hall at ρ = 10% carries 22 MW of allocated IT. If draw exceeds the cap in 0.5% of hours, that is ≈ 44 capped hours a year. Raise ρ while the extra MW earn more than the extra capped hours cost, and only while critical workloads stay within ε.
00.51.0Cluster power / PmaxTime (one step ≈ sub-second to tens of seconds; amplitude scales with job size)computeall-reducecheckpointrawshaped (floor + storage)
Figure 3Illustrative training power trace (not measured). Dashed: shaped profile.

See UC 03, UC 04 · Power Stabilization for AI Training Datacenters, arXiv:2508.14318

NOTE 07

Metrics that lie: PUE, fan power and water

DecisionWhich efficiency metric enters the objective.

Remove server fans and PUE can rise while total energy falls. Report TUE.

PUE = E_facility / E_IT TUE = PUE × ITUE ITUE = E_IT / E_compute WUE = L_site_water / kWh_IT
Illustrative: 100 kW of IT at PUE 1.20 draws 120 kW. Remove 8 kW of server fans with liquid cooling and keep 20 kW of facility overhead: IT falls to 92 kW, total to 112 kW (−6.7%), yet PUE rises to 1.22. Optimise total energy per unit of compute, not PUE.

See UC 07 · ISO/IEC 30134-2, -9

NOTE 08

TCO under uncertainty

DecisionHow to choose between designs whose costs are uncertain.

Over-provisioning for the coincident worst case is expensive. Price the tail instead.

TCO(x, ω) = CapEx(x) + Σ_t [ E(t)·PUE(t)·p_e(t) + W(t)·p_w + failures(T,RH)·c_r + SLA(caps) ] / (1+r)^t min_x E_ω[TCO] + λ · CVaR_α[TCO] s.t. P[excursion] ≤ ε
Illustrative: design A has E[TCO] = 100 and CVaR0.95 = 118; design B has 97 and 131. With λ = 0.3, A scores 135.4 and B 136.3: A wins despite the higher mean, because B’s bad scenarios are worse. λ is set with you, before the numbers are run.

See UC 05, UC 06.

NOTE 09

Goodput: failures, checkpoints and the cost of scale

DecisionSpares, checkpoint interval and storage bandwidth for a large training cluster.

Cluster MTBF falls as 1/N. At large N, checkpoint and restart policy is a capacity decision.

M_cluster ≈ M_device / N (independent failures) τ* ≈ √(2 · δ · M_cluster) (Young, first order) waste ≈ δ / τ + (τ/2 + R) / M_cluster goodput ≈ 1 − waste
Illustrative: N = 16,384 accelerators at 50,000 h MTBF each gives Mcluster ≈ 3.1 h. With δ = 2 min to write a checkpoint and R = 10 min to restart, τ* ≈ 27 min and goodput ≈ 80%. Halving δ lifts it to ≈ 84%. Spares, failure domains, storage bandwidth and power floors all move these terms, so we size them together.

See UC 03 · Young, Commun. ACM 1974, doi · Daly, Future Gener. Comput. Syst. 2006, doi